An owner withholds 10% retention on a $40,000 progress billing. How much does the contractor receive on that billing?
a.$40,000
b.$36,000
c.$30,000
d.$4,000
解析
Retention withheld = $40,000 x 10% = $4,000. Amount paid now = $40,000 - $4,000 = $36,000. The $4,000 is held back and released later, typically after completion.