商业财务第 1150 / 1605 题
On most California public works projects, retention withheld by the public entity is generally limited to a maximum of:
a.5%
b.15%
c.20%
d.10%
解析
Public Contract Code §7201 generally caps retention on public works at 5% absent a finding that the project is substantially complex. This limit helps contractors' cash flow. Private contracts commonly use 10% but are set by agreement.
法律依据: Public Contract Code §7201免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A contractor's bond is a form of surety bond. This means:
- An owner withholds 10% retention on a $40,000 progress billing. How much does the contractor receive on that billing?
- The primary purpose of retention (retainage) on a construction contract is to:
- A contractor completes a $250,000 job on which the owner withheld 10% retention throughout. Assuming no deductions, how much retention should be released at closeout?
- Progress billing (progress payments) means the contractor:
- On a home improvement contract, the down payment a contractor may collect is limited by law to whichever is less: