A contractor completes a $250,000 job on which the owner withheld 10% retention throughout. Assuming no deductions, how much retention should be released at closeout?
a.$12,500
b.$2,500
c.$25,000
d.$225,000
解析
Total retention = 10% of the $250,000 contract = $25,000. Once the work is accepted and any lien/warranty conditions are met, the full $25,000 retention is released to the contractor.