Drainage, Waste & Vent第 14 / 120 题

A 4 in horizontal building drain runs 340 ft under a warehouse slab. Not counting the cleanout at the upstream end of the run, what is the minimum number of additional cleanouts required for spacing alone?

a.2
b.3
c.4
d.6

解析

Horizontal drainage lines 4 in and smaller require a cleanout at intervals not exceeding 100 ft, so a 340 ft run needs cleanouts at roughly 100, 200, 300 ft and at the far end, which is 3 additional cleanouts beyond the upstream one to keep every interval at or under 100 ft. Two cleanouts would leave intervals longer than 100 ft, while 4 and 6 exceed the minimum the spacing rule requires.

法律依据: UPC §708.3.3