Drainage, Waste & Vent第 16 / 120 题
A 6 in horizontal drainage line requires a cleanout. What is the minimum size of the cleanout opening?
a.4 in
b.3 in
c.5 in
d.6 in
解析
A cleanout must be the same nominal size as the pipe it serves for pipe up to 4 in, and pipe larger than 4 in requires a cleanout of at least 4 in. A 6 in cleanout is larger than the code minimum, and 3 in and 5 in do not match either the same-size rule or the 4 in cap.
免费刷完整 120 道题库 — 无需注册。
同考点相关题目
- Which fitting is required to change direction from horizontal to horizontal in a drainage line?
- A 4 in horizontal building drain runs 340 ft under a warehouse slab. Not counting the cleanout at the upstream end of the run, what is the minimum number of additional cleanouts required for spacing alone?
- A cleanout is installed on a 2 in horizontal waste line in a finished room. What is the minimum clearance required in front of the cleanout?
- Under the UPC, where does the building drain end and the building sewer begin?
- A single 3 in vent stack is 46 ft in developed length and serves a drainage stack. If the code limits a given vent size to a maximum developed length, exceeding that length requires which action?
- Two lavatories are installed back to back on opposite sides of a wall and discharge into the same double fitting at the same level. What vent arrangement is being used?