8 questions

Michigan Contracting Law & Unlicensed Practice

An unlicensed Michigan builder completes residential work and then sues the homeowner for the unpaid balance. Under MCL 339.2412, what is the result?

  • a.The builder may collect the full contract price
  • b.The builder may collect the cost of materials only
  • c.The builder may not bring or maintain a court action to collect compensation for the work
  • d.The homeowner must pay double damages

Under MCL 339.2412, a builder who was unlicensed when the work was performed may not bring or maintain an action in any Michigan court to collect compensation for that work — losing the right to sue for either the contract price or the value of labor and materials.MCL 339.2412

Michigan Contracting Law & Unlicensed Practice

Under the Michigan Construction Lien Act, within what time after last furnishing labor or materials must a claimant record a Claim of Lien?

  • a.Within 90 days
  • b.Within 30 days
  • c.Within one year
  • d.Within 10 days

The Michigan Construction Lien Act (MCL 570.1101 et seq.) requires a Claim of Lien to be recorded within 90 days after the claimant last furnished labor or materials to the project.Michigan Construction Lien Act, MCL 570.1101 et seq.

Michigan Contracting Law & Unlicensed Practice

After recording a Claim of Lien in Michigan, within what time must the claimant start a proceeding to enforce (foreclose) the lien?

  • a.Within 90 days of recording
  • b.Within one year of recording the Claim of Lien
  • c.Within 30 days of recording
  • d.There is no deadline once the lien is recorded

Under the Construction Lien Act, a claimant must commence a proceeding to enforce the lien within one year after the Claim of Lien is recorded, or the lien is lost.Michigan Construction Lien Act, MCL 570.1117

Michigan Contracting Law & Unlicensed Practice

A Michigan subcontractor not in direct contract with the owner wants to preserve construction-lien rights. What step is generally required soon after starting work?

  • a.Recording a Claim of Lien before any work begins
  • b.Filing a lawsuit within 10 days
  • c.Nothing; lien rights attach automatically with no notice
  • d.Serving a Notice of Furnishing, generally within 20 days of first furnishing labor or materials

Under the Construction Lien Act, a claimant not contracting directly with the owner generally must serve a Notice of Furnishing within 20 days of first furnishing labor or materials to preserve lien rights.Michigan Construction Lien Act (Notice of Furnishing)

Michigan Contracting Law & Unlicensed Practice

Which of the following is a recognized ground for the Michigan board to discipline a residential builder?

  • a.Fraud or a substantial departure from accepted construction standards, or failing to account for money or property received
  • b.Charging market-rate prices for work
  • c.Hiring licensed subcontractors
  • d.Carrying more insurance than the minimum

Article 24 of the Occupational Code lists grounds for discipline including fraud, a bad-faith or substantial departure from accepted construction standards, and failing to properly account for money or property received from an owner.MCL 339.2411 (grounds for discipline)

Michigan Contracting Law & Unlicensed Practice

What must appear on a licensed Michigan residential builder's contracts and advertising?

  • a.The builder's home address only
  • b.The name of the homeowner's bank
  • c.The builder's license number
  • d.Nothing is required to be shown

A licensed Michigan builder must display the license number on contracts and advertising, part of the consumer-protection framework that distinguishes a licensed builder from an unlicensed operator.Michigan residential-builder contract / advertising rules

Michigan Contracting Law & Unlicensed Practice

Why is holding a valid Michigan license so important to a builder's ability to get paid?

  • a.It only lowers permit fees
  • b.Because an unlicensed builder cannot sue to collect, licensure is a precondition to using the courts to enforce payment
  • c.It has no effect on collection rights
  • d.It doubles the amount the builder can charge

Because MCL 339.2412 bars an unlicensed builder from suing to collect, a builder must be licensed at the time of the work to preserve the right to enforce payment through the courts.MCL 339.2412 (effect of licensure on collection)

Michigan Contracting Law & Unlicensed Practice

In Michigan, acting as a residential builder without the required license, in addition to barring a suit to collect, may also result in:

  • a.A tax refund to the builder
  • b.Automatic issuance of a license
  • c.A warning with no other consequence in any case
  • d.Criminal penalties for unlicensed practice

Unlicensed residential contracting in Michigan is not only a bar to collecting through the courts; it is a violation of the Occupational Code that can carry criminal penalties in addition to the loss of collection rights.MCL 339.2403 (unlicensed practice)

Report