North Carolina General Contractor Exam — All Questions

← Back to practice

4 questions

Estimating & Bidding

A contractor's total direct cost for a job is $18,000. The contractor adds a 15% markup to cover overhead and profit. What is the bid price?

  • a.$18,150
  • b.$18,270
  • c.$20,700
  • d.$21,150

Markup is a percentage added on top of cost. Multiply the cost by (1 + markup): $18,000 x 1.15 = $20,700. The markup dollars are $18,000 x 0.15 = $2,700, which is added to the $18,000 cost to reach the bid price. Markup covers both company overhead and profit.

Estimating & Bidding

A job costs the contractor $8,000. The contractor wants a 20% gross profit MARGIN (profit as a percentage of the selling price). What must the selling price be?

  • a.$9,600
  • b.$10,000
  • c.$9,800
  • d.$10,400

Margin is measured against the selling price, not the cost, so you cannot simply add 20% to cost. Price = cost / (1 - margin) = $8,000 / (1 - 0.20) = $8,000 / 0.80 = $10,000. Check: profit is $2,000, and $2,000 / $10,000 = 20% margin. Adding 20% to cost ($9,600) would only give a 16.7% margin — a common and costly estimating error.

Estimating & Bidding

How many cubic yards of concrete are needed for a slab 27 ft long, 30 ft wide, and 4 inches thick?

  • a.3.3 cubic yards
  • b.6.7 cubic yards
  • c.8.5 cubic yards
  • d.10 cubic yards

First convert thickness to feet: 4 in / 12 = 0.3333 ft. Volume in cubic feet = 27 x 30 x 0.3333 = 270 cubic feet. Convert to cubic yards by dividing by 27 (there are 27 cubic feet in a cubic yard): 270 / 27 = 10 cubic yards. Getting units consistent — feet for all three dimensions — is the key step.

Estimating & Bidding

On a project where the exact quantities of excavation and fill are not yet known, which bidding method best protects both owner and contractor from large quantity surprises?

  • a.A unit-price contract, paying a set price per unit for the actual quantity installed
  • b.A lump-sum contract with no measurement of quantities
  • c.A verbal handshake agreement
  • d.A cost-plus contract with no cost records kept

Unit pricing sets a fixed price per unit (for example, per cubic yard of excavation), and the contractor is paid for the actual measured quantity. This fairly handles uncertain quantities: the owner pays only for work performed, and the contractor is protected if quantities grow. A lump sum forces the contractor to guess and gamble on the quantity, which is risky when the amount is genuinely unknown.

Report