Core TradesQuestion 106 of 700
Asphalt shingles are blowing off in high winds shortly after installation. The MOST likely installation error is:
a.Too many nails per shingle
b.Nails driven too deep is impossible
c.Using the correct nail placement
d.Nails placed too high above the nailing strip or overdriven/underdriven, so they miss the shingle above
Explanation
Fasteners placed above the designated nailing zone, or overdriven/underdriven, fail to secure both the shingle and the tab of the course above, causing wind blow-off. Using the correct placement would not cause failure, and too many nails is not the typical cause of blow-off.
Law Reference: 2025 CA Building Code, Chapter 15 (Roof Assemblies)Practice all 700 questions free — no signup required.
Related questions on this topic
- At the intersection of two sloping roof planes, water collects and flows in a channel. The flashing installed in this channel is called:
- Where a sloped shingle roof meets a vertical sidewall, the correct flashing method is:
- On a low-slope shingle roof, underlayment courses must be lapped so water sheds over each lower course. The MAIN reason for the larger head and side laps on low slopes is:
- Counter flashing at a chimney is installed so that its top edge is embedded in or tucked into a mortar joint of the masonry, MAINLY to:
- CALCULATION: Roofing is estimated in squares (1 square = 100 square feet). A gable roof has two rectangular planes, each 40 feet by 25 feet. How many squares of roofing are needed, before waste?
- In cold climates, an ice barrier (self-adhering membrane) is applied at the eaves of a shingle roof MAINLY to: