Core TradesQuestion 126 of 700

The primary purpose of providing an adequate lap length where two reinforcing bars overlap is to:

a.Reduce the amount of concrete required
b.Increase the slump of the surrounding concrete
c.Allow the forms to be stripped sooner
d.Transfer tensile stress continuously between the bars

Explanation

A lap splice lets the bond between steel and concrete transfer tensile force from one bar into the next so the reinforcement acts continuously. An inadequate lap creates a weak point where the steel cannot develop its strength. Lapping has nothing to do with concrete quantity, slump, or form-stripping time.

Practice all 700 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review
Report