A continuous footing is 12 inches wide, 12 inches deep, and 60 feet long. How many cubic yards of concrete are required (before waste)?
a.1.7 cubic yards
b.2.2 cubic yards
c.3.3 cubic yards
d.6.7 cubic yards
Explanation
12 inches equals 1 foot, so the cross-section is 1 ft x 1 ft = 1 sq ft. Volume = 1 x 60 = 60 cubic feet. Divide by 27: 60 / 27 = 2.2 cubic yards. 6.7 comes from dividing by 9 instead of 27; the other choices are arithmetic errors.
Practice all 700 questions free — no signup required.
Related questions on this topic
- Assuming proper placement and curing, which change to a concrete mix will produce the GREATEST increase in compressive strength?
- For a one-story wood-frame dwelling on stable soil with no deeper frost-line requirement, what is the MINIMUM depth below the undisturbed ground surface to the bottom of an exterior footing?
- The primary purpose of providing an adequate lap length where two reinforcing bars overlap is to:
- A slump test on fresh concrete is performed primarily to measure the concrete's:
- Standard-cured concrete test cylinders are most commonly broken to verify that the specified compressive strength (f'c) has been reached at what age?
- A patio slab is 16 ft by 20 ft and 6 inches thick. Including a 10% allowance for waste and spillage, how much concrete should be ordered?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review