Core TradesQuestion 130 of 700

A patio slab is 16 ft by 20 ft and 6 inches thick. Including a 10% allowance for waste and spillage, how much concrete should be ordered?

a.5.9 cubic yards
b.6.0 cubic yards
c.6.5 cubic yards
d.8.0 cubic yards

Explanation

6 inches = 0.5 ft. Volume = 16 x 20 x 0.5 = 160 cubic feet = 160 / 27 = 5.93 cubic yards. Add 10%: 5.93 x 1.10 = 6.5 cubic yards. 5.9 ignores the waste allowance; the other values are too high or from mis-conversion.

Practice all 700 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review
Report