Framing & StructuralQuestion 355 of 700

Fiber-cement lap siding is installed on a wood-framed wall. What clearance is generally required between the bottom edge of the siding and the finished grade or a roof surface below it?

a.No clearance; siding may touch the ground
b.A clearance (commonly around 6 inches to earth and about 1 to 2 inches above a roof) to keep the siding out of standing water and splash
c.At least 12 inches above a roof
d.Siding must be buried 2 inches into the grade

Explanation

Manufacturers and the code call for clearance at the bottom of fiber-cement (and most) siding, commonly about 6 inches to earth and roughly 1 to 2 inches above roof surfaces, to keep the siding out of standing water and splash that would wick moisture. No clearance, 12 inches above a roof, or burying the siding are incorrect.

Law Reference: 2025 CA Residential Code §R703.3

Practice all 700 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review