Planning & EstimatingQuestion 503 of 700
During a field inspection you notice the delivered floor joists are one size smaller than the joists specified on the approved structural plans. What is the BEST first step?
a.Install them anyway to keep the schedule and note it later
b.Stop that installation and verify the discrepancy against the plans and structural engineer before proceeding
c.Cut the joists to fit and add extra nails
d.Order paint so finishes can start on schedule
Explanation
A joist smaller than specified reduces load capacity and can be a life-safety defect. The BEST first step is to stop, verify the discrepancy against the approved plans, and consult the structural engineer before any framing is installed. Installing anyway (a) or field-modifying members (c) can compromise the structure and lead to failed inspections. Option d ignores the structural issue entirely.
Practice all 700 questions free — no signup required.
Related questions on this topic
- You are preparing a critical path schedule. Which sequence of activities BEST reflects proper project coordination for a slab-on-grade building?
- A concrete slab is 30 ft by 40 ft and 4 inches thick. How many cubic yards of concrete are required?
- A bedroom plan shows a single egress window with a clear opening of 5.0 square feet and a sill 46 inches above the finished floor. Based on typical emergency escape requirements, what should the plan checker flag?
- A parking lot is 200 ft by 300 ft and will receive 3 inches of asphalt. Approximately how many cubic yards of compacted asphalt are needed?
- When performing a quantity takeoff from a set of plans, which practice BEST reduces costly estimating errors?
- A project must meet CALGreen construction waste requirements. What is the general contractor's BEST approach to demonstrate compliance during the job?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review