A parking lot is 200 ft by 300 ft and will receive 3 inches of asphalt. Approximately how many cubic yards of compacted asphalt are needed?

a.About 185 cubic yards
b.About 370 cubic yards
c.About 556 cubic yards
d.About 1,667 cubic yards

Explanation

Area = 200 x 300 = 60,000 sq ft. Thickness = 3 in = 0.25 ft. Volume = 60,000 x 0.25 = 15,000 cubic feet. Cubic yards = 15,000 / 27 = about 556. Option d forgets to convert thickness. Option a divides incorrectly. Convert the depth to feet, multiply by the area, then divide by 27 for cubic yards.