Planning & EstimatingQuestion 504 of 700
A parking lot is 200 ft by 300 ft and will receive 3 inches of asphalt. Approximately how many cubic yards of compacted asphalt are needed?
a.About 185 cubic yards
b.About 370 cubic yards
c.About 556 cubic yards
d.About 1,667 cubic yards
Explanation
Area = 200 x 300 = 60,000 sq ft. Thickness = 3 in = 0.25 ft. Volume = 60,000 x 0.25 = 15,000 cubic feet. Cubic yards = 15,000 / 27 = about 556. Option d forgets to convert thickness. Option a divides incorrectly. Convert the depth to feet, multiply by the area, then divide by 27 for cubic yards.
Practice all 700 questions free — no signup required.
Related questions on this topic
- A concrete slab is 30 ft by 40 ft and 4 inches thick. How many cubic yards of concrete are required?
- A bedroom plan shows a single egress window with a clear opening of 5.0 square feet and a sill 46 inches above the finished floor. Based on typical emergency escape requirements, what should the plan checker flag?
- During a field inspection you notice the delivered floor joists are one size smaller than the joists specified on the approved structural plans. What is the BEST first step?
- When performing a quantity takeoff from a set of plans, which practice BEST reduces costly estimating errors?
- A project must meet CALGreen construction waste requirements. What is the general contractor's BEST approach to demonstrate compliance during the job?
- A supplier quotes framing lumber at $650 per thousand board feet (MBF). A job requires 8,000 board feet. What is the estimated material cost before tax?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review