Planning & EstimatingQuestion 507 of 700
A supplier quotes framing lumber at $650 per thousand board feet (MBF). A job requires 8,000 board feet. What is the estimated material cost before tax?
a.$3,250
b.$5,200
c.$650
d.$52,000
Explanation
Price is $650 per 1,000 board feet. For 8,000 board feet: 8,000 / 1,000 = 8 units, times $650 = $5,200. Option d multiplies by 8,000 instead of 8. Option a uses half the quantity. When pricing is quoted per MBF, divide the total board feet by 1,000 before multiplying by the unit price.
Practice all 700 questions free — no signup required.
Related questions on this topic
- A parking lot is 200 ft by 300 ft and will receive 3 inches of asphalt. Approximately how many cubic yards of compacted asphalt are needed?
- When performing a quantity takeoff from a set of plans, which practice BEST reduces costly estimating errors?
- A project must meet CALGreen construction waste requirements. What is the general contractor's BEST approach to demonstrate compliance during the job?
- A general contractor coordinates multiple subcontractors on a commercial project. Which practice BEST prevents schedule conflicts and duplicated work between trades?
- A room measures 14 ft by 16 ft with 9 ft high walls. You must apply two coats of paint to the walls only. Deducting one 3 ft x 7 ft door and two 3 ft x 4 ft windows, and assuming coverage of 350 sq ft per gallon per coat, what is the MINIMUM whole number of gallons to buy?
- A room is 12 ft by 20 ft with 8 ft ceilings. You will hang 4 ft by 8 ft gypsum board on all four walls and the ceiling, ignoring openings and waste. What is the MINIMUM number of full sheets needed?