A 'balanced' grading design PRIMARILY seeks to:
a.Make the cut volume equal the fill volume so no soil is imported or exported
b.Keep all finished surfaces perfectly level
c.Remove the maximum possible amount of topsoil
d.Place fill only, with no excavation anywhere on site
Explanation
A balanced site is graded so that excavated (cut) material equals the material needed for fill, minimizing costly hauling on or off site. It does not require level surfaces, maximum topsoil removal, or fill-only work.
Practice all 700 questions free — no signup required.
Related questions on this topic
- In a basic (non-high-wind) zone, standard asphalt shingles are typically fastened with a MINIMUM of how many nails per shingle?
- A simple gable roof covers a building 24 feet by 40 feet in plan. At a 6:12 pitch (slope factor 1.118), what is the approximate total roof surface area?
- In differential leveling, a 'backsight' reading is taken on:
- Which field method determines in-place soil density by excavating a small hole and replacing the soil with a calibrated sand from a known-volume cone?
- In soil compaction, the maximum dry density of a soil is achieved when it is compacted at its:
- Under Cal/OSHA rules, a trench that workers enter must be protected by shoring, sloping, or a shield system once its depth reaches at least:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review