Planning & EstimatingQuestion 602 of 700
A common rafter has a horizontal run of 15 ft on a roof with a 5-in-12 slope (5 inches of rise per 12 inches of run). Ignoring overhang, what is the APPROXIMATE rafter length from ridge to top plate?
a.15 ft
b.16.25 ft
c.21.25 ft
d.19.5 ft
Explanation
Rise = 15 x (5 / 12) = 6.25 ft. Rafter length = sqrt(run^2 + rise^2) = sqrt(15^2 + 6.25^2) = sqrt(225 + 39.06) = sqrt(264.06) = 16.25 ft (b). (This is a 5-12-13 triangle: 15 / 12 x 13 = 16.25.) Option (a) is the run only. Option (c) adds run and rise instead of using the hypotenuse. Option (d) overestimates the slope factor.
Practice all 700 questions free — no signup required.
Related questions on this topic
- A base rock pad is 36 ft by 50 ft, placed 4 inches thick. If compacted base rock weighs about 1.35 tons per cubic yard, APPROXIMATELY how many tons are needed?
- A footing has 3 continuous #4 rebars, each running 120 ft. Using #4 bar at about 0.668 pounds per linear foot, what is the APPROXIMATE total weight of steel?
- A CMU wall requires 450 blocks. Using a rule of about 3 bags of mortar per 100 blocks, what is the MINIMUM number of mortar bags to order?
- A slab-on-grade is 20 ft by 30 ft and 4 inches thick, with a thickened (turndown) edge around the full perimeter that adds a beam 12 in wide by 12 in deep below the slab. What is the APPROXIMATE total concrete volume?
- An excavation is 20 ft by 30 ft and 5 ft deep. After digging, the soil swells 25 percent for hauling. APPROXIMATELY how many loose cubic yards must be hauled away?
- A wall is 9 ft high and 40 ft long and will be covered with 4x8 sheathing panels. Ignoring openings, what is the MINIMUM number of full sheets (round up)?