An excavation is 20 ft by 30 ft and 5 ft deep. After digging, the soil swells 25 percent for hauling. APPROXIMATELY how many loose cubic yards must be hauled away?
a.111 cubic yards
b.3,000 cubic yards
c.125 cubic yards
d.139 cubic yards
Explanation
Bank volume = 20 x 30 x 5 = 3,000 cubic feet. Divide by 27: 3,000 / 27 = 111.1 bank cubic yards. Apply 25 percent swell: 111.1 x 1.25 = 138.9, about 139 loose cubic yards (d). Option (a) ignores swell. Option (b) leaves cubic feet without dividing by 27. Option (c) applies only about a 12 percent swell.
Practice all 700 questions free — no signup required.
Related questions on this topic
- A CMU wall requires 450 blocks. Using a rule of about 3 bags of mortar per 100 blocks, what is the MINIMUM number of mortar bags to order?
- A common rafter has a horizontal run of 15 ft on a roof with a 5-in-12 slope (5 inches of rise per 12 inches of run). Ignoring overhang, what is the APPROXIMATE rafter length from ridge to top plate?
- A slab-on-grade is 20 ft by 30 ft and 4 inches thick, with a thickened (turndown) edge around the full perimeter that adds a beam 12 in wide by 12 in deep below the slab. What is the APPROXIMATE total concrete volume?
- A wall is 9 ft high and 40 ft long and will be covered with 4x8 sheathing panels. Ignoring openings, what is the MINIMUM number of full sheets (round up)?
- When preparing a material takeoff, why does an estimator add a waste/allowance factor to the net measured quantities?
- A crew of 3 workers works 5 days at 8 hours per day. At a fully burdened rate of $52 per hour, what is the estimated labor cost?