Planning & EstimatingQuestion 606 of 700
When preparing a material takeoff, why does an estimator add a waste/allowance factor to the net measured quantities?
a.To increase the profit margin built into the bid
b.To cover material lost to cuts, breakage, trimming, and overlap so enough is delivered
c.Because building codes require a fixed 20 percent surplus on every material
d.So the plans do not have to be measured accurately
Explanation
A waste factor accounts for real field losses: offcuts, breakage, trimming, pattern matching, and overlap, so the ordered quantity actually finishes the work (b). It is not profit (a) - that is added separately as overhead and profit. There is no code-mandated fixed 20 percent surplus (c). And it never substitutes for an accurate takeoff (d); waste is added on top of an accurate measurement.
Practice all 700 questions free — no signup required.
Related questions on this topic
- A slab-on-grade is 20 ft by 30 ft and 4 inches thick, with a thickened (turndown) edge around the full perimeter that adds a beam 12 in wide by 12 in deep below the slab. What is the APPROXIMATE total concrete volume?
- An excavation is 20 ft by 30 ft and 5 ft deep. After digging, the soil swells 25 percent for hauling. APPROXIMATELY how many loose cubic yards must be hauled away?
- A wall is 9 ft high and 40 ft long and will be covered with 4x8 sheathing panels. Ignoring openings, what is the MINIMUM number of full sheets (round up)?
- A crew of 3 workers works 5 days at 8 hours per day. At a fully burdened rate of $52 per hour, what is the estimated labor cost?
- A tile installer prices work at $9.50 per square foot installed. For a job of 850 square feet, what is the estimated installed cost?
- Your takeoff shows 14 cubic yards of concrete needed, and the supplier quotes $185 per cubic yard delivered. What is the estimated material cost for the concrete?