SafetyQuestion 647 of 700
A temporary cover is placed over a floor opening in a walkway. Which set of requirements BEST describes a compliant hole cover?
a.It must be painted red only, with no strength requirement
b.It only needs to fully hide the hole from view
c.It must be removable by hand at any time and left unsecured for quick access
d.It must support at least twice the maximum intended load, be secured against displacement, and be marked to warn of the hazard
Explanation
Correct: a compliant floor-hole cover must carry at least twice the maximum intended load (workers, equipment, materials), be secured so it cannot shift or be accidentally removed, and be marked (e.g., 'HOLE' or 'COVER') to warn workers. Color alone, hiding the hole, or leaving it loose for 'quick access' all fail the securing, strength, and marking requirements.
Practice all 700 questions free — no signup required.
Related questions on this topic
- A standard guardrail system is used as the primary fall protection along an open edge. In any outward or downward direction, the top rail must be able to withstand a MINIMUM applied load of about how much without failing?
- On a guardrail system protecting an edge where tools could fall onto workers below, a toeboard is added. About what MINIMUM height must the toeboard rise above the walking surface?
- A worker on a wall form uses a device that holds them in place and lets them lean back to work hands-free, limiting any fall to no more than 2 feet. This describes which system?
- Safety nets are chosen as fall protection under a leading edge. Which pair of requirements is correct for safety nets?
- A supported scaffold and its components are being specified. Each part of the scaffold and its supports must be capable of holding at least how many times the maximum intended load without failure?
- Wood platform planks on a scaffold are supported at each end. Where planks are overlapped rather than butted, the overlap must occur over a support and extend at least how far past the centerline of the support?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review