A subpanel is fed from the main service panel in a detached structure. In a modern installation, the neutral (grounded) and equipment grounding (ground) conductors at the subpanel must be:
a.Kept separate, with the neutral bus isolated from the enclosure
b.Bonded together at the subpanel
c.Both left floating
d.Connected only through the metal conduit
Explanation
At a subpanel the neutral and ground must be kept separate, with the neutral bus isolated from the metal enclosure, so normal neutral current does not flow on grounding conductors and metal parts. Bonding neutral and ground is done only at the service disconnect, not at downstream subpanels.
Law Reference: 2025 CA Electrical Code (based on NEC)Practice all 700 questions free — no signup required.
Related questions on this topic
- In a typical dwelling, the interior metal water piping and the metal gas piping are required to be:
- An electrical panel is being installed. Regarding circuit identification, the code requires that:
- CALCULATION: A single-phase load draws 24 amperes at 240 volts. What is the apparent power in kilovolt-amperes (kVA)?
- A homeowner reports that a bedroom outlet works but the tester shows an open ground. The MOST likely cause is:
- CALCULATION: A branch circuit is protected by a 20-ampere breaker. Applying the common rule that a continuous load should not exceed 80 percent of the breaker rating, what is the maximum continuous load in amperes?
- When routing a nonmetallic-sheathed cable through holes bored in wood studs, the code generally requires that the hole be kept back from the stud edge, or a steel plate be installed, primarily to:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review