Equipment & SystemsQuestion 305 of 521

A legally required standby system must restore power to its loads within what maximum time after normal supply is lost?

a.10 seconds
b.30 seconds
c.60 seconds
d.120 seconds

Explanation

Section 701.12 requires that a legally required standby system supply its loads within 60 seconds of a normal-supply failure. The 10-second figure applies to true emergency systems (Article 700), which serve life-safety loads that need faster restoration.

Law Reference: 2023 NEC §701.12