Testing & TroubleshootingQuestion 484 of 521

Before performing a continuity test on a cable with an ohmmeter, what condition must exist?

a.The circuit must be de-energized (no voltage present)
b.The circuit must be energized at full load
c.The conductor must be under 120 V
d.The neutral must be bonded to a driven ground rod

Explanation

An ohmmeter/continuity function supplies its own small test voltage; applying it to a live circuit gives false readings and can damage the meter or injure you. The conductor must be de-energized and isolated. Energizing (b, c) defeats the test, and grounding a rod (d) is unrelated.