Contracts & ExecutionQuestion 152 of 1632

A "guaranteed maximum price" (GMP) contract protects the owner because:

a.The contractor is paid a lump sum whatever the costs run
b.The owner pays no more than the agreed ceiling price
c.The owner pays cost plus a fee with no ceiling at all
d.Savings below the ceiling belong to the contractor

Explanation

A guaranteed maximum price reimburses cost up to a negotiated ceiling and the contractor absorbs anything above it, which is exactly what caps the owner's exposure. A lump sum paid regardless of what the costs run is a stipulated-sum contract, a different form with a different split of risk. Cost plus a fee with no ceiling is the open cost-plus arrangement a GMP exists to cap. And an underrun below the ceiling belongs to the owner unless a shared-savings clause says otherwise, so treating the savings as the contractor's reverses the deal.

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report