Contracts & ExecutionQuestion 151 of 690

A grading contract pays $4.50 per cubic yard of soil excavated, with the final quantity measured in the field. This is a:

a.Unit-price contract
b.Lump sum contract
c.Cost-plus contract
d.Guaranteed maximum price contract

Explanation

A unit-price contract sets a price per unit of work (per cubic yard, per linear foot, etc.). The total contract value depends on the actual measured quantities completed.

Practice all 690 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Report