Contracts & ExecutionQuestion 169 of 690
A job was estimated at $40,000 in labor but actual labor came in at $48,000. This $8,000 difference is BEST described as:
a.A cost overrun (unfavorable variance)
b.A contingency allowance
c.A retention amount
d.Liquidated damages
Explanation
When actual cost exceeds the estimate, the shortfall is a cost overrun, also called an unfavorable variance. Job costing flags such variances so the contractor can investigate the cause.
Practice all 690 questions free — no signup required.
Related questions on this topic
- On a $500,000 contract, the schedule of values shows framing as 18% of the total. If framing is 50% complete, how much may the contractor bill for framing this period?
- A contractor completes $80,000 of work in a billing period. The contract provides for 10% retention. How much should the contractor expect to receive for this progress payment?
- The primary purpose of job costing during a project is to:
- When a general contractor relies on a subcontractor's bid to prepare its prime bid, the sub generally:
- The practice of a general contractor revealing one subcontractor's bid to a competitor to obtain a lower price is called:
- A contractor discovers a $20,000 arithmetic error in its bid one hour after submitting it, before any contract is signed. The contractor's BEST course of action is to:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review