Contracts & ExecutionQuestion 166 of 690
On a $500,000 contract, the schedule of values shows framing as 18% of the total. If framing is 50% complete, how much may the contractor bill for framing this period?
a.$25,000
b.$45,000
c.$90,000
d.$250,000
Explanation
Framing's total value is 18% x $500,000 = $90,000. At 50% complete the contractor may bill 50% x $90,000 = $45,000 for that line item this period.
Practice all 690 questions free — no signup required.
Related questions on this topic
- After a project is satisfactorily completed and accepted on a private works job, the owner must release retention to the general contractor within:
- After receiving retention from the owner, a general contractor on a private works project must pass through each subcontractor's retention within:
- In a construction contract, a "schedule of values" is BEST described as:
- A contractor completes $80,000 of work in a billing period. The contract provides for 10% retention. How much should the contractor expect to receive for this progress payment?
- The primary purpose of job costing during a project is to:
- A job was estimated at $40,000 in labor but actual labor came in at $48,000. This $8,000 difference is BEST described as:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review