Contracts & ExecutionQuestion 165 of 690
In a construction contract, a "schedule of values" is BEST described as:
a.A breakdown of the contract price allocated among the parts of the work, used to support progress billings
b.A list of every employee's hourly wage
c.The contractor's overhead allocation worksheet
d.A calendar showing inspection dates
Explanation
A schedule of values divides the total contract sum among the various components of the work. Each progress payment application bills the percentage complete of each line item against this schedule.
Practice all 690 questions free — no signup required.
Related questions on this topic
- If an owner wrongfully withholds an undisputed progress payment from a general contractor, California prompt payment law allows a penalty of:
- After a project is satisfactorily completed and accepted on a private works job, the owner must release retention to the general contractor within:
- After receiving retention from the owner, a general contractor on a private works project must pass through each subcontractor's retention within:
- On a $500,000 contract, the schedule of values shows framing as 18% of the total. If framing is 50% complete, how much may the contractor bill for framing this period?
- A contractor completes $80,000 of work in a billing period. The contract provides for 10% retention. How much should the contractor expect to receive for this progress payment?
- The primary purpose of job costing during a project is to:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review