On a $150,000 contract, the owner withholds 5% retention from each progress payment. After all work is billed, how much money is being held as retention?
Explanation
Retention = 5% x $150,000 = $7,500 (b), held by the owner until the project is accepted, which the contractor must plan for in its cash flow. Civil Code §8811 caps private-works retention at 5% for contracts entered into on or after January 1, 2026, and Public Contract Code §7201 sets the same ceiling on most public works. (c) $15,000 applies the 10% that was customary on private jobs before 2026. (d) $142,500 is the amount paid out, not the amount held. (a) $1,500 is 1%, a decimal slip.
This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A contractor's quick (acid-test) view of liquidity differs from the current ratio mainly because the quick ratio:
- A contractor borrows $30,000 at 6% simple annual interest and repays it in full after 3 years. What is the total amount repaid?
- A contractor's fixed monthly costs total $18,000 and variable costs run 60% of revenue. What monthly revenue is needed to break even?
- Why does retention (retainage) create a cash-flow challenge for a contractor?
- Including a contingency line item in a project budget is intended to:
- Which of the following is a VARIABLE cost that rises and falls with the volume of construction work performed?
Last reviewed: · editorial process