Business FinancesQuestion 306 of 690

On a $150,000 contract, the owner withholds 10% retention from each progress payment. After all work is billed, how much money is being held as retention?

a.$1,500
b.$15,000
c.$13,500
d.$135,000

Explanation

Retention = 10% × $150,000 = $15,000. This amount is held by the owner until the project is accepted, which the contractor must plan for in its cash flow.