A subcontractor served a proper preliminary notice but the owner never paid. Before recording a mechanics' lien, the subcontractor should make sure the lien claim states an amount that is:
Explanation
§8430(a) makes the lien a direct lien for the lesser of two amounts: the reasonable value of the work the claimant provided, and the price agreed with whoever contracted for that work. §8430(c) adds that where the contract was rescinded, abandoned or breached the lien may not exceed reasonable value. So the ceiling is the unpaid value of what was actually furnished, which is what (b) ignores — money already received has to come off the claim. (a) treats interest and fees as if they were principal, and they are not part of the lien amount. (d) confuses the security with the debt: the lien attaches to the property, but its size is measured by the work. The sanction behind all of this is §8422(c) — a claimant who willfully includes labour, services, equipment or materials never furnished for that property forfeits the lien entirely — while §8422(a) forgives an honest error in the demand. The preliminary notice this subcontractor served matters separately: §8410 lets a claimant enforce a lien only if that notice was given and proof of it made.
Law Reference: Civil Code §8430(a), (c); §8422(a), (c); §8410This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A design-build contractor makes a professional design error that causes a client financial loss but no bodily injury or property damage. Which coverage is specifically intended for this kind of claim?
- Which of the following parties is generally NOT entitled to record a mechanics' lien on a private construction project?
- On a private project where NO Notice of Completion or Cessation is recorded, what deadline applies to ALL claimants for recording a mechanics' lien?
- On a private project, an owner who wants to shorten the time claimants have to record liens should:
- A contractor recorded a valid mechanics' lien but, 100 days later, has neither been paid nor filed a foreclosure lawsuit. What is the status of the lien?
- A subcontractor signs a lien waiver in exchange for a progress payment that has not yet actually cleared. Which type of waiver is appropriate so the waiver only takes effect once payment is received?
Last reviewed: · editorial process