On a private project where NO Notice of Completion or Cessation is recorded, what deadline applies to ALL claimants for recording a mechanics' lien?
Explanation
With no notice recorded, both halves of the scheme land on the same date. §8412 gives the direct contractor until the earlier of 90 days after completion of the work of improvement or 60 days after the owner records a notice of completion or cessation; §8414 gives every other claimant the earlier of 90 days after completion or 30 days after such a notice. Take the notice away and only the 90-day branch is left, for everybody — which is exactly what makes recording a notice worth the owner's trouble. So (a) borrows the 30-day figure that exists only once a notice has been recorded. (b) starts the clock at signature, a date the lien statutes never use. (c) is out by a factor of four, though it sits near a real rule: under §8460(b), where claimant and owner record an extension of credit, the action to enforce can run up to a year after completion of the work. And recording is only the first half of the job — §8460(a) then requires the action to enforce the lien within 90 days of recordation, or the claim of lien expires and is unenforceable.
Law Reference: Civil Code §8412; §8414; §8460(a)-(b)This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A contractor's employee causes an accident while driving a company truck to a job site. Which policy is primarily intended to respond to the resulting third-party vehicle and injury claims?
- A design-build contractor makes a professional design error that causes a client financial loss but no bodily injury or property damage. Which coverage is specifically intended for this kind of claim?
- Which of the following parties is generally NOT entitled to record a mechanics' lien on a private construction project?
- A subcontractor served a proper preliminary notice but the owner never paid. Before recording a mechanics' lien, the subcontractor should make sure the lien claim states an amount that is:
- On a private project, an owner who wants to shorten the time claimants have to record liens should:
- A contractor recorded a valid mechanics' lien but, 100 days later, has neither been paid nor filed a foreclosure lawsuit. What is the status of the lien?
Last reviewed: · editorial process