Insurance & LiensQuestion 480 of 690
A subcontractor signs a lien waiver in exchange for a progress payment that has not yet actually cleared. Which type of waiver is appropriate so the waiver only takes effect once payment is received?
a.An unconditional waiver and release
b.A Notice of Completion
c.A conditional waiver and release
d.A lien release bond
Explanation
A conditional waiver and release becomes effective only when the claimant actually receives the payment. An unconditional waiver releases lien rights immediately and should not be signed until payment has truly cleared.
Law Reference: Civil Code §8136Practice all 690 questions free — no signup required.
Related questions on this topic
- A subcontractor served a proper preliminary notice but the owner never paid. Before recording a mechanics' lien, the subcontractor should make sure the lien claim states an amount that is:
- On a private project, an owner who wants to shorten the time claimants have to record liens should:
- A contractor recorded a valid mechanics' lien but, 100 days later, has neither been paid nor filed a foreclosure lawsuit. What is the status of the lien?
- A subcontractor records a $40,000 mechanics' lien on a home that the owner is trying to sell. To clear title so the sale can close, the owner records a lien release bond. The bond amount must be:
- An owner of a private residential project withholds final payment because of disputed change-order work. Absent a genuine good-faith dispute, the owner must generally pay the direct contractor the final retention within how long after completion?
- On a private work of improvement, a supplier serves a stop payment notice on the construction lender. To make the notice "bonded" so the lender is obligated to withhold funds, the supplier should provide a bond equal to:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review