Insurance & LiensQuestion 482 of 690
An owner of a private residential project withholds final payment because of disputed change-order work. Absent a genuine good-faith dispute, the owner must generally pay the direct contractor the final retention within how long after completion?
a.10 days
b.20 days
c.30 days
d.45 days
Explanation
Under Civil Code §8800, on a private work the owner must pay the direct contractor any retention within 45 days after completion of the work of improvement, unless there is a good-faith dispute. Wrongful withholding can expose the owner to a penalty plus the amount withheld.
Law Reference: Civil Code §8800Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor recorded a valid mechanics' lien but, 100 days later, has neither been paid nor filed a foreclosure lawsuit. What is the status of the lien?
- A subcontractor signs a lien waiver in exchange for a progress payment that has not yet actually cleared. Which type of waiver is appropriate so the waiver only takes effect once payment is received?
- A subcontractor records a $40,000 mechanics' lien on a home that the owner is trying to sell. To clear title so the sale can close, the owner records a lien release bond. The bond amount must be:
- On a private work of improvement, a supplier serves a stop payment notice on the construction lender. To make the notice "bonded" so the lender is obligated to withhold funds, the supplier should provide a bond equal to:
- A contractor abandons a private project before it is finished and the owner records a Notice of Cessation after work stops for a continuous period. The Notice of Cessation primarily serves to:
- An employee is injured on the job while working for an employer who has unlawfully failed to obtain workers' compensation insurance. Under California Labor Code §3706, the injured employee may:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review