Insurance & LiensQuestion 482 of 690

An owner of a private residential project withholds final payment because of disputed change-order work. Absent a genuine good-faith dispute, the owner must generally pay the direct contractor the final retention within how long after completion?

a.10 days
b.20 days
c.30 days
d.45 days

Explanation

Under Civil Code §8800, on a private work the owner must pay the direct contractor any retention within 45 days after completion of the work of improvement, unless there is a good-faith dispute. Wrongful withholding can expose the owner to a penalty plus the amount withheld.

Law Reference: Civil Code §8800

Practice all 690 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Report