Insurance & LiensQuestion 481 of 690
A subcontractor records a $40,000 mechanics' lien on a home that the owner is trying to sell. To clear title so the sale can close, the owner records a lien release bond. The bond amount must be:
a.$40,000, equal to the lien
b.$20,000, half the lien
c.$50,000, which is 125% of the lien
d.$80,000, which is double the lien
Explanation
Under Civil Code §8424, a lien release bond must be 125% of the claimed lien amount. For a $40,000 lien, that is $50,000. The bond substitutes as security so the claimant's recovery shifts from the property to the bond.
Law Reference: Civil Code §8424Practice all 690 questions free — no signup required.
Related questions on this topic
- On a private project, an owner who wants to shorten the time claimants have to record liens should:
- A contractor recorded a valid mechanics' lien but, 100 days later, has neither been paid nor filed a foreclosure lawsuit. What is the status of the lien?
- A subcontractor signs a lien waiver in exchange for a progress payment that has not yet actually cleared. Which type of waiver is appropriate so the waiver only takes effect once payment is received?
- An owner of a private residential project withholds final payment because of disputed change-order work. Absent a genuine good-faith dispute, the owner must generally pay the direct contractor the final retention within how long after completion?
- On a private work of improvement, a supplier serves a stop payment notice on the construction lender. To make the notice "bonded" so the lender is obligated to withhold funds, the supplier should provide a bond equal to:
- A contractor abandons a private project before it is finished and the owner records a Notice of Cessation after work stops for a continuous period. The Notice of Cessation primarily serves to:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review