Public WorksQuestion 618 of 690
On a California public works contract, after the awarding body accepts the work as complete, retention proceeds must generally be released to the prime contractor within:
a.30 days, or interest accrues at the legal rate
b.60 days after the date of completion, or a 2% per month penalty (24% annualized) may accrue on improperly withheld amounts
c.90 days, with no statutory penalty for delay
d.120 days after final acceptance by the awarding body
Explanation
Public Contract Code §7107 requires public agencies to release retention proceeds to the prime contractor within 60 days after the date of completion of the work, and primes must pay their subs within 7 days after receipt. Wrongful withholding triggers a charge of 2% per month (about 24% per year) on improperly withheld amounts, plus attorneys' fees in the resulting action. The 30-day option confuses retention release with general progress payment timing, and the 90/120-day options exceed the §7107 statutory window.
Law Reference: Public Contract Code §7107Practice all 690 questions free — no signup required.
Related questions on this topic
- Under Labor Code §1771.5, a public agency may exempt a public works project from prevailing wage requirements only if the project does not exceed:
- California's general prevailing wage requirement applies to public works projects exceeding what threshold?
- Under Labor Code §1775, what is the maximum statutory penalty per worker per day for a contractor's willful underpayment of prevailing wages on a public works project?
- Under California's Subletting and Subcontracting Fair Practices Act, a prime contractor bidding on a public works project must list each subcontractor whose work exceeds:
- After bid opening on a public works project, the prime contractor wants to substitute a different subcontractor for one listed in the bid. Under Public Contract Code §4107, the substitution is generally permitted only if:
- Under Labor Code §1777.5 and Title 8 CCR §230.1, the apprentice-to-journeyman ratio on a public works project for the craft in question is generally:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review