A change order on a home improvement contract is enforceable only if it is:
Explanation
B&P §7159(c)(5) makes a change-order form part of a home improvement contract only if it is in writing and signed by the parties prior to the commencement of any work covered by the change order; §7159(d)(13) requires the contract itself to say so under the heading Note About Extra Work and Change Orders. A daily job log is the contractor's own record, not the owner's signature. The CSLB licenses and disciplines contractors; it does not pre-approve change orders. And no percentage of the contract price lets a contractor change the work unilaterally - that is the practice §7159 was written to stop.
Law Reference: B&P Code §7159(c)(5); §7159(d)(13)This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A subcontract contains a 'flow-down' clause stating the sub assumes toward the prime all obligations the prime owes the owner under the prime contract. The effect of this clause is that the subcontractor:
- A subcontract requires the sub to name the prime contractor and owner as ADDITIONAL INSUREDS on the sub's commercial general liability policy AND to provide a WAIVER OF SUBROGATION. The PRIMARY purpose of the waiver of subrogation is to:
- Under Bus. & Prof. Code §7159, a residential home improvement contract for $500 or more must include, in close proximity to the signature line, a notice informing the owner of the right to:
- Under Bus. & Prof. Code §7191, a residential construction contract that contains a binding arbitration clause must:
- Bus. & Prof. Code §7159 requires home improvement contracts to include the approximate dates when work will begin and when it will be substantially complete. If the contractor fails to commence the work within a reasonable time from the agreed start date, the consumer's primary remedy is to:
- An $80,000 residential remodel contract contains both a binding arbitration clause and a separate mandatory mediation clause. Under B&P §7191, the MEDIATION clause must:
Last reviewed: · editorial process