A preliminary notice on a private construction project must be served on:
Explanation
§8200(a) names three recipients: the owner or reputed owner, the direct contractor to which the claimant provides work, and the construction lender if there is one. §8200(c) and (d) make that service a prerequisite to a valid lien claim, stop payment notice, or claim against a payment bond. The real exceptions run the other way from these distractors: §8200(e) excuses a laborer entirely and requires a claimant who does have a direct contract with the owner to notify only the construction lender. (b) drops the owner, whose property the lien attaches to; (c) adds the building department, which has no role in the lien scheme; and (d) confuses the preliminary notice with recording the claim of lien itself at the recorder's office.
Law Reference: Civil Code §8200(a), (c)-(e)This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A subcontractor begins work on a private project on March 1. To preserve lien rights, the preliminary notice must be served by:
- After completion of a private project, a claimant has how many days to record a mechanics' lien if no Notice of Completion is filed?
- If the owner records a Notice of Completion, subcontractors and suppliers must record their mechanics' lien within:
- After recording a mechanics' lien, the claimant must file a lawsuit to enforce the lien within:
- What is the purpose of a "stop payment notice" on a private construction project?
- An owner can release a recorded mechanics' lien by obtaining a lien release bond equal to:
Last reviewed: · editorial process