Insurance & LiensQuestion 73 of 690

A subcontractor begins work on a private project on March 1. To preserve lien rights, the preliminary notice must be served by:

a.March 1
b.March 21
c.April 1
d.Within 20 days of first furnishing labor or materials

Explanation

On private works, preliminary notices must be served within 20 days of first furnishing labor, services, equipment, or materials. Serving late does not eliminate lien rights entirely but limits them to work performed within 20 days before service.

Law Reference: Civil Code §8204

Practice all 690 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Report