A subcontractor begins work on a private project on March 1. To preserve lien rights, the preliminary notice must be served by:
Explanation
Civil Code §8200 requires the preliminary notice to be served not later than 20 days after the claimant first furnishes labor, service, equipment, or materials, so work starting March 1 puts the deadline at March 21. (a) treats the notice as a condition of starting work; it is not, and a notice served on day one is valid but early. (b) borrows a ten-day period that appears elsewhere in construction practice, not here. (c) rounds to a month. Late service does not destroy the lien outright: under §8204 it limits the claim to work furnished in the 20 days before service and afterwards.
Law Reference: Civil Code §8200 / §8204This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A preliminary notice on a private construction project must be served on:
- After completion of a private project, a claimant has how many days to record a mechanics' lien if no Notice of Completion is filed?
- If the owner records a Notice of Completion, subcontractors and suppliers must record their mechanics' lien within:
- After recording a mechanics' lien, the claimant must file a lawsuit to enforce the lien within:
- What is the purpose of a "stop payment notice" on a private construction project?
- An owner can release a recorded mechanics' lien by obtaining a lien release bond equal to:
Last reviewed: · editorial process