Insurance & LiensQuestion 73 of 1632

A subcontractor begins work on a private project on March 1. To preserve lien rights, the preliminary notice must be served by:

a.March 1, the day the work first began
b.March 11, ten days after work first began
c.April 1, one month after work first began
d.March 21, twenty days after work first began

Explanation

Civil Code §8200 requires the preliminary notice to be served not later than 20 days after the claimant first furnishes labor, service, equipment, or materials, so work starting March 1 puts the deadline at March 21. (a) treats the notice as a condition of starting work; it is not, and a notice served on day one is valid but early. (b) borrows a ten-day period that appears elsewhere in construction practice, not here. (c) rounds to a month. Late service does not destroy the lien outright: under §8204 it limits the claim to work furnished in the 20 days before service and afterwards.

Law Reference: Civil Code §8200 / §8204

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report