Contracts & ExecutionQuestion 72 of 1632

A contractor is hired to build a room addition. After completion, the homeowner claims defects. The contractor's written warranty on new residential construction must be at least:

a.90 days
b.1 year
c.2 years
d.The contractor sets the term freely

Explanation

California's Right to Repair Act (SB 800) establishes statutory warranties for new residential construction: 1 year for most components, 4 years for plumbing/electrical/mechanical, 10 years for structural defects.

Law Reference: Civil Code §896

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report