Contracts & ExecutionQuestion 72 of 690
A contractor is hired to build a room addition. After completion, the homeowner claims defects. The contractor's written warranty on new residential construction must be at least:
a.90 days
b.1 year
c.2 years
d.The contractor sets the term freely
Explanation
California's Right to Repair Act (SB 800) establishes statutory warranties for new residential construction: 1 year for most components, 4 years for plumbing/electrical/mechanical, 10 years for structural defects.
Law Reference: Civil Code §896Practice all 690 questions free — no signup required.
Related questions on this topic
- A subcontractor fails to complete their scope of work on a project. The prime contractor's primary recourse is:
- California's "prompt payment" law requires owners to pay general contractors within how many days of a proper invoice?
- A general contractor must pay a subcontractor within how many days of receiving payment from the owner?
- On a $40,000 home improvement contract, what is the maximum down payment a contractor may legally demand or accept before work begins?
- On a $6,000 home improvement contract, what is the maximum allowable down payment?
- Which of the following is NOT a required element of a California home improvement contract?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review