A subcontractor fails to complete their scope of work on a project. The prime contractor's primary recourse is:
Explanation
When a subcontractor defaults, the prime's contract remedy is to terminate that subcontract, have the scope finished by others, and recover the difference from the defaulting sub — or from its performance bond, if one was furnished. (a) CSLB discipline can suspend or revoke the sub's license, but the Registrar has no power to order the work completed or to make the prime whole; that is a court's or an arbitrator's job. (d) A change order moves the cost onto the owner, who neither caused the default nor agreed to pay twice for the same scope. (c) Walking off is worse than useless: abandoning a project without legal excuse is itself cause for discipline under B&P §7107, so the prime would trade a collection claim for a license problem.
Law Reference: Bus. & Prof. Code §7107 (abandonment); §7108.5 (payments to subcontractors)This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A contractor must provide an owner with a "Notice to Owner" (preliminary notice) primarily to:
- Under a "time and materials" (T&M) contract, the owner pays:
- Which contract type places the MOST financial risk on the contractor?
- California's "prompt payment" law requires owners to pay general contractors within how many days of a proper invoice?
- On a private project, a direct (general) contractor receives a progress payment from the owner. Within how many days must it pay each subcontractor that subcontractor's share?
- A contractor is hired to build a room addition. After completion, the homeowner claims defects. The contractor's written warranty on new residential construction must be at least:
Last reviewed: · editorial process