Contracts & ExecutionQuestion 67 of 690
Under a "time and materials" (T&M) contract, the owner pays:
a.A fixed price agreed upon before work starts
b.Only the material costs; labor is the contractor's responsibility
c.A set hourly rate with no material reimbursement
d.Actual costs of labor and materials plus an agreed markup or fee
Explanation
A T&M contract pays the contractor for actual labor hours at an agreed rate plus actual material costs, typically plus overhead and profit markup. The total cost is not fixed in advance.
Practice all 690 questions free — no signup required.
Related questions on this topic
- A contract clause that shifts responsibility for delays outside the contractor's control to the owner is called:
- An owner includes a liquidated damages clause of $500 per day for late completion. This clause is enforceable if:
- A contractor must provide an owner with a "Notice to Owner" (preliminary notice) primarily to:
- Which contract type places the MOST financial risk on the contractor?
- A subcontractor fails to complete their scope of work on a project. The prime contractor's primary recourse is:
- California's "prompt payment" law requires owners to pay general contractors within how many days of a proper invoice?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review