Which contract type places the MOST financial risk on the contractor?
Explanation
Under a fixed-price lump sum contract the contractor promises a finished result for one price, so every overrun - labor productivity, material escalation, rework - lands on the contractor. Cost-plus-a-fixed-fee reverses that: the owner reimburses actual costs and the fee is fixed, so the owner carries the overrun. Time and materials bills hours and materials as they are incurred, which again leaves the cost risk with whoever pays the invoices. A unit price contract fixes only the rate per unit installed; the quantity risk stays with the owner, and the contractor is exposed only on its own productivity per unit.
Law Reference: -This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- An owner includes a liquidated damages clause of $500 per day for late completion. This clause is enforceable if:
- A contractor must provide an owner with a "Notice to Owner" (preliminary notice) primarily to:
- Under a "time and materials" (T&M) contract, the owner pays:
- A subcontractor fails to complete their scope of work on a project. The prime contractor's primary recourse is:
- California's "prompt payment" law requires owners to pay general contractors within how many days of a proper invoice?
- On a private project, a direct (general) contractor receives a progress payment from the owner. Within how many days must it pay each subcontractor that subcontractor's share?
Last reviewed: · editorial process