Contracts & ExecutionQuestion 71 of 1605

A general contractor must pay a subcontractor within how many days of receiving payment from the owner?

a.3 days
b.7 days
c.10 days
d.30 days

Explanation

Because payment comes from the owner, this is a private project. Under Civil Code §8814 (and B&P §7108.5), a direct (general) contractor must pay each subcontractor its share within 7 days of receiving a progress payment from the owner, or face a 2%-per-month penalty. Ten days is the separate deadline for releasing withheld retention to a subcontractor — not the progress-payment rule this question asks about.

Law Reference: Civil Code §8814

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report