Insurance & LiensQuestion 75 of 690

After completion of a private project, a claimant has how many days to record a mechanics' lien if no Notice of Completion is filed?

a.30 days
b.60 days
c.90 days
d.180 days

Explanation

If no Notice of Completion or Cessation is recorded, a mechanics' lien must be recorded within 90 days of completion of the project. This is the maximum window for lien claimants.

Law Reference: Civil Code §8412

Practice all 690 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Report