Insurance & LiensQuestion 75 of 163264% of test-takers answer this correctly

After completion of a private project, a claimant has how many days to record a mechanics' lien if no Notice of Completion is filed?

a.30 days
b.60 days
c.90 days
d.180 days

Explanation

If no Notice of Completion or Cessation is recorded, a mechanics' lien must be recorded within 90 days of completion of the project. This is the maximum window for lien claimants.

Law Reference: Civil Code §8412; §8414

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report