Insurance & LiensQuestion 75 of 690
After completion of a private project, a claimant has how many days to record a mechanics' lien if no Notice of Completion is filed?
a.30 days
b.60 days
c.90 days
d.180 days
Explanation
If no Notice of Completion or Cessation is recorded, a mechanics' lien must be recorded within 90 days of completion of the project. This is the maximum window for lien claimants.
Law Reference: Civil Code §8412Practice all 690 questions free — no signup required.
Related questions on this topic
- A subcontractor begins work on a private project on March 1. To preserve lien rights, the preliminary notice must be served by:
- A preliminary notice on a private construction project must be served on:
- If the owner records a Notice of Completion, subcontractors and suppliers must record their mechanics' lien within:
- After recording a mechanics' lien, the claimant must file a lawsuit to enforce the lien within:
- What is the purpose of a "stop payment notice" on a private construction project?
- An owner can release a recorded mechanics' lien by obtaining a lien release bond equal to:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review