Insurance & LiensQuestion 75 of 1605

After completion of a private project, a claimant has how many days to record a mechanics' lien if no Notice of Completion is filed?

a.30 days
b.60 days
c.90 days
d.180 days

Explanation

If no Notice of Completion or Cessation is recorded, a mechanics' lien must be recorded within 90 days of completion of the project. This is the maximum window for lien claimants.

Law Reference: Civil Code §8412

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report