Insurance & LiensQuestion 1520 of 1605

A subcontractor serves a stop payment notice on the private owner (not bonded). The owner is then obligated to:

a.Record the notice with the recorder
b.Immediately pay the subcontractor in full
c.Withhold sufficient undisbursed funds from the direct contractor to cover the claim plus a reasonable allowance for litigation costs
d.Ignore the notice unless it is bonded

Explanation

Civil Code §8534 provides that a stop payment notice to the owner obligates the owner to withhold from the direct contractor money sufficient to answer the claim plus a reasonable allowance for costs. A bond is required to bind a lender, but not to bind the owner.

Law Reference: Civ. Code §8534

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report