Business FinancesQuestion 1155 of 1605

Under the schedule-of-values method of progress billing, each payment application is based on:

a.A flat monthly fee regardless of progress
b.The contractor's overhead rate
c.The percentage of each line item of work completed to date
d.The sales tax collected that month

Explanation

A schedule of values breaks the contract price into line items. Each progress billing states the percentage of each item completed to date, and payment is the earned value less previous payments and retention. This ties billings directly to actual progress.

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)