SafetyQuestion 1301 of 1605

Which is a required control when performing higher-risk (Class I) asbestos removal?

a.Regulated areas, negative-pressure enclosures, wet methods, and respiratory protection
b.No controls if done quickly
c.Only a paper dust mask
d.Open-air dry removal

Explanation

Class I asbestos work requires stringent controls: regulated areas, critical barriers/negative-pressure enclosures, wet methods, HEPA filtration, and appropriate respirators to prevent fiber release.

Law Reference: 29 CFR 1926.1101