While replacing a section of galvanized water piping in a building from the 1950s, a plumber finds an adjacent steam line wrapped in crumbling fibrous insulation and sees that the old water joints were made with 50/50 tin-lead solder. What is the correct response?
Explanation
Deteriorating pipe insulation in a building of that era is presumed asbestos-containing until sampling proves otherwise, and the correct action is to leave it alone, keep others out of the area and report it so licensed abatement personnel handle the removal. Cutting, scraping or wetting it yourself still releases fibers and does not make an untrained worker an abatement contractor, and a filtering facepiece does not authorize the work either. On the piping side, 50/50 tin-lead solder is prohibited in potable water systems; solder and flux must be lead free, and wetted surfaces of pipe, fittings and fixtures must not exceed a weighted average lead content of 0.25 percent.
Practice all 120 questions free — no signup required.
Related questions on this topic
- A crew is setting sewer pipe in a trench 5 ft 6 in deep with vertical walls cut in previously disturbed soil. No sloping, shoring or shielding has been installed. What does OSHA require before a worker enters?
- A trench 7 ft deep with a 3 ft wide bottom is excavated in Type C soil and will be protected by sloping the walls at 1-1/2 to 1. How wide must the excavation be at the top?
- A trench 5 ft deep and 90 ft long is open, with workers spread along its full length installing pipe. What is the minimum number of ladders required and how must they be placed?
- A trench must be excavated 22 ft deep in Type B soil to reach an existing sewer main. Which statement about the protective system and the excavated material is correct?
- Before anyone enters a 12 ft deep sewer manhole classified as a permit-required confined space, the atmosphere is tested and the meter reads 19.2 percent oxygen. What is the correct interpretation, and in what order must the atmosphere be tested?
- A plumber is brazing copper joints in a finished mechanical room with combustible wood framing a few feet away. Which practice meets the fire prevention requirements for the work?
Last reviewed: · editorial process