Around a new window, the correct flashing sequence to integrate with the WRB is generally:
a.Head flashing first, then jambs, then sill
b.All four sides at once with sealant only
c.Sill flashing first, then jambs, then head flashing lapped over the WRB above
d.Only the head needs flashing
Explanation
The proper shingle-lap sequence is sill pan flashing first, then jamb flashing over the sill, then head flashing with the WRB above lapping over the head flashing, so each layer sheds onto the one below. Doing the head first, all at once with sealant, or head-only all trap water.
Law Reference: 2025 CA Building Code / CRC (Weather Protection)Practice all 700 questions free — no signup required.
Related questions on this topic
- CALCULATION: A wall assembly has three layers with R-values of R-4 (sheathing), R-13 (cavity), and R-0.68 (interior finish). Ignoring air films, what is the total nominal R-value?
- An air barrier is installed in a building envelope MAINLY to:
- A water-resistive barrier (WRB) is being installed over wall sheathing. To shed water correctly, the horizontal laps must be arranged so that:
- Behind exterior stucco or siding, a drainage gap or weep provision is often required so that:
- Fiberglass batt insulation is compressed and stuffed tightly around wiring and into a cavity that is too shallow. The effect on thermal performance is:
- In a mixed California climate, a vapor retarder placed on the WRONG side of the insulation can cause:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review