CALCULATION: A wall assembly has three layers with R-values of R-4 (sheathing), R-13 (cavity), and R-0.68 (interior finish). Ignoring air films, what is the total nominal R-value?
a.R-13
b.R-15
c.R-17.68
d.R-20
Explanation
For layers in series, R-values add: 4 + 13 + 0.68 = 17.68. Answer 13 counts only the cavity; 15 and 20 add incorrectly.
Law Reference: 2025 CA Energy Code (Title 24, Part 6)Practice all 700 questions free — no signup required.
Related questions on this topic
- In cold climates, an ice barrier (self-adhering membrane) is applied at the eaves of a shingle roof MAINLY to:
- Proper sequencing of roof components requires that water always flows over, not under, the layer below. Therefore drip edge at the eave and underlayment should be arranged so that:
- Continuous insulation (ci) is applied on the exterior side of the wall sheathing, over the studs, MAINLY to:
- An air barrier is installed in a building envelope MAINLY to:
- A water-resistive barrier (WRB) is being installed over wall sheathing. To shed water correctly, the horizontal laps must be arranged so that:
- Around a new window, the correct flashing sequence to integrate with the WRB is generally:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB General Building (B) Trade Examination · How we review